Major Road Projects

  • Chip sealing is done for the season.
  • Microsurfacing work is being done in the Quinn & Silver City areas. 
  • Pavement markings are about ½ done for the season. 
  • FMG has submitted plans to DOT for final review to prepare to bid this fall for the Reservoir Road/Lamb Rd project.

Major Bridge Projects

  • Bridge preservation work has had its pre-construction meeting and is waiting for a start date.

Division Updates

Hill City
  • 1 culvert replaced on Black Fox
  • 2 culverts replaced on W Deerfield
  • 1 metal culvert replaced on OHC (Old Hill City Rd)
  • Multiple concrete culverts repaired on OHC
  • Hauling chips for chip seal, helping with RC chip seal
  • Blading
  • Reno Gulch Drainage project
  • Fall mowing starting soon
New Underwood
  • Blading gravel
  • Training new employee in the Motorgrader
  • 173rd drainage work
  • Cleaned up the shop
  • Helped Rapid City with Chip Seal
  • Culvert replaced on 173rd
Rapid City
  • Deep Patch – worked on approaches and patched the sinkhole on Sharp Dr.
  • AMZ – North of town
  • Fog/Prime seal for 225th & Old Folsom; cement stabilization
  • Guardrail maintenance
  • Ashland Heights area prepped for prime. Primed and sanded Ashland area and Hidden Springs
  • Chip sealed with the help of New Underwood and Hill City hauling chips
  • Gravel maintenance
Wall
  • Mag Water – completed Elm Springs & Creighton
  • Patching – Creighton base, subgrade repair capped with base course
  • Blading
  • Mowing 3 days of contract roads
  • Culvert maint/drainage – 4 days on Quinn Rd and 3 days on Wilsey Rd
  • Fall mowing starting in the next couple of weeks

Major Weather Events

  • There was a bad hailstorm that occurred on August 11th in the Rockerville area. Crews plowed and swept hail, pine needles, pine cones, and branches. Then, the next day, swept all Rally roads.
  • We have also had several localized significant rainfall events.